In March, Ride Blue Mountains President met Ryan Hawkin, BMCC, Glenbrook Tunnel Project Manager, for an update on the expenditure of the Department Planning and Environment tunnel remediation grant. Council has cleared the tunnel of waste left by the previous mushroom farm tenants. Council reports that the brickwork and tunnel floor construction are in good condition.
Next Steps include:
- completing the clearing of tunnel gully between the eastern portal and water tank and repairing drains so water can be redirected and dewatering the eastern portal;
- tender for lights for the tunnel and construction of a crush stone surface as interim measure until funds are available for a sealed path
- commissioning a precinct plan, heritage and other reports
At this stage it is hoped construction on the path will occur in the second half of 2024 and the tunnel will be open to the public from either the end of 2024 or early 2025.
Work on the Precinct plan will commence in June and Council will be consulting with Ride Blue and other key stakeholders in the development of the plan. The precinct plan aims to provide a detailed plan of how the Tunnel and Tunnel Gully will integrate with the Scenic Eastern Escarpment Master Plan. The plan will present an opportunity to build on the connections set out in Ride Blue Mountains’ Concept Plan and tell a story/ narrative of how the assets will work to provide walking, cycling, rail heritage, passive recreation, events and tourism experiences. In other words, how the assets will help make the Eastern Escarpment a destination. It is also an opportunity to revisit trail management in Knapsack and Explorers Reserves and the connections between both areas. Ride Blue has reached out to some other key stakeholders in the lead up to Council’s engagement to understand the perspectives of other user groups and also to seek input to develop some agreed principles to help guide Council’s plan including:
- how the plan will work in the context of a broader regional plan which covers the river precincts, lakes, aerotropolis and so on; and
- how the eastern escarpment could therefore be part of a broader regional tourism plan which attracts visitors for multi-day stays (including visitors coming to Sydney through the new airport).
This is an important piece of work because it will be the driver for not just planning and design but also future funding as the ideas must be pitched to investors, including the NSW Government.Â